Shelton Road Bridge Replacement - Wolf River Lateral J

Project Status Update

Legend: Completed    Current Phase

Shelton Road Bridge Replacement - Wolf River Lateral J

State: Tennessee
TN Lead Agency(ies): Collierville
Bridge
2020
130858.00
STP-M-2014-12
Status:
Contract Execution
PE-NEPA
PE-Design
ROW/Utilities
CONST (Pre. Con)

 

ROW underway